Connecting electricity to the house yourself with your own hands: Instruction + Video and Photo

Connecting electricity to the house yourself with your own hands: Instruction + Video and Photo Connection to the mains of a private house. A person who owns a country house who wants to independently make an electricity connection, but has no idea where to start this procedure.

To make it easier, it is worth considering the classic situation: The required power is up to 15 kW, the House or cottage is located in the village.

Connection. Steps

  • Connecting electricity to the house yourself with your own hands: Instruction + Video and Photo Submitting an application for connection to the nearest electricity company.

  • Obtaining and familiarization with documentation and technical specifications from the power grid organization.
  • Conclusion of a contract.
  • Execution of works on both sides, prescribed in the technical conditions. The customer is on his site, the organization is outside.
  • Power is being connected and power is being supplied to power-consuming devices.

  • Signing of the contract.

This is the usual scheme, because most often the connection to the power supply is done in this way. But there are certain nuances that you definitely need to know before you start collecting documents.

First, you should find out about the presence of an electrical network nearby, with the power you need, as well as find out the distance from the house to them. This point is worth focusing on.

After all, it is precisely this distance that is the decisive factor for setting the timing and prices for connecting electricity.

You have the right to request information about the location of the network. This service is absolutely free.

List of documents

About the list of documents that must be submitted to the RES produces a lot of disputes on the topic of connecting electricity. Below is a standard list of documents for connecting a house to electricity.

Application

Here you should specify :

  • Connecting electricity to the house yourself with your own hands: Instruction + Video and Photo Details of the applicant.
  • Passport data.
  • Location of the facility where electricity will be supplied (address with house number).

Maintenance

  1. Scheme of connecting electricity in the house, with the indicated energy consumers, indicating their location and number.
  2. Documents confirming the ownership of private property.

Attention: The specific list of documents should be found out in your organization, as this list may be different in different regions.

Terms of electricity connection

Within one month from the date of application, the organization must issue to the applicant:

  1. - Agreement
  2. - TU (upon receipt, the applicant has 30 days to sign them)

If the applicant has not enclosed any documents in the application, then the electric grid organization has the right to inform him within six working days.

We advise you to carefully read all documents before signing them. Such an order is that if you do not agree with the conditions put forward by the company, then within one month you have the right to send a justified refusal to the organization.

The company has a period of no more than six months to connect to the electrical network, from the moment of signing the contract.

Pressure levers

Some may encounter difficulties, for example, the organization connecting electricity did not issue an agreement for TP and TU, or did not meet within the time limit allotted by law.

In order to defend yourself, you need to know:

  • According to the norms of our time, the power plant is obliged to conduct an electric line no further than 25 meters from the site the applicant.
  • The procedure for connecting to the networks of a grid organization is regulated by the Rules for technological connection of power receiving devices. This is prescribed by the Government of the Russian Federation. Resolution No.

    861 of December 27, 2004;

  • Since the power grid companies are monopoly, they have protection from competitors before the law.
  • Company data are regulated. If they deviate from legal obligations, then the company may be fined.

Connection options

There are only two options for conducting electricity - the transmission of energy through the air and underground, through a closed dense cable.

The first option will be several times cheaper than the second, since you will spend a significant amount of money on the materials.

  1. Air line. In this embodiment, a cable is pulled from the support to ensure the supply of electricity to the switchboard. This is not at all difficult to do, but you must definitely follow the connection rules. For this, a SIP cable is usually used. This is a wire with excellent insulation, thanks to the wire inside it is not afraid of the wind.

    It can have two cores for a single-phase network, and for a two-phase network it has four cores. If the distance exceeds the standards, it is worth installing more supports.

  2. Underground. This option is visually more aesthetic, but considerable material costs will be required. A special underground cable is required, which is much more expensive than SIP.

    The principle of conducting electricity by this method is practically no different from the option of an overhead line.

.